CDM Registration of the Jorethang Loop Hydroelectric Power Project

Region: South Asia

Facts and Figures

Client Sector Energy Supply
Type Hydroelectric Project
Capacity 96 MW
Period 2005 - ongoing
Energy Output 440,000 MWh pa
Location Sikkim, India
Carbon Credits 465,000 CERs per annum
Project Commissioning Date 1st January 2010 (proposed)

View more in these categories:

Clean development mechanism (CDM)

This project involved the registration of a 96 MW run of the river hydro electric project in Sikkim, India (http://cdm.unfccc.int/Projects/DB/DNV-CUK1188881385.79/view).  Tasks undertaken included the preparation of a Project Concept Note and Project Design Document, consultation with stakeholders and the local community, facilitation of host country approval, engagement and management of a Designated Operational Entity for validation and verification. Currently assisting the client with the commercialisation of the CERs generated.